Weekly Project Updates

December 20, 2019
Pleasant Hill Road improvements continue. Contractor Ghilotti Brothers, Inc. continues to form and pour concrete curbs for the new medians along the project corridor working from Taylor Boulevard south to Gregory Lane; to date, the vertical curb between Taylor Boulevard to Linda Lane has been substantially completed. Linda to Mercury is currently being formed. Electrical subcontractor Columbia Electric continues to install conduits for new street lights and the new signal interconnect system within the medians, with work completed to Westover Lane as they work south to Valley View. Starting next week, the contractor will be off for the holidays for two weeks and resume construction activities on Jan. 6. Some minor activities may be scheduled. Due to the weather, activities are being scheduled as site conditions permit. Northbound traffic continues to be limited to one lane between Valley View Road and Linda Lane at all times. All work is on schedule and this phase of the project should be completed (weather permitting) by May 2020.
PHR

November 22, 2019
Removal of the concrete medians is complete. For the next two weeks, contractor Ghilotti Brothers, Inc will excavate and off haul masses of tree roots from the median area, lay out locations for new street lights, and install conduits for street lights and traffic signals. Northbound traffic will continue to be limited to one lane between Valley View Drive and Linda Lane at all times. Temporary lane closures in the southbound direction will continue when traffic is light. Motorists may encounter delays. Lane closures are intended to protect the contractor and the public while work is being performed in the medians. All work is expected to be completed by mid-April 2020. A second project to reconstruct the pavement will follow.

PHR
November 8, 2019
Contractor Ghilotti Brothers, Inc. continues working on the Pleasant Hill Road Improvement Project, Phase 1 (Gregory Lane to Taylor Boulevard). Construction operations for the next three weeks includes removal and replacement of the concrete medians along the corridor. Beginning Nov. 12, northbound traffic will be limited to one lane between Valley View Drive and Linda Lane at all times. Southbound traffic will be limited to one lane when traffic is light. Motorists should expect delays. Lane closures are being implemented to protect the contractor and the public while work is being done in the center medians.
PHR1